Quantcast
Channel: CUBIX PROJECT MANAGEMENT - 3D Work Breakdown Structure method
Viewing all articles
Browse latest Browse all 86

Part #77: What is a 3D structured schedule?

$
0
0

A 3D structured schedule is a schedule done with 3D WBS method.


The elementary tree structures are crossed to create the list of tasks, the three natures of logical links (Zone, Product and Activity) are defined, and the durations are calculated inside the 3 dimensions of the WBS. Cubix 360 software can be used to create the schedule.


The result is a well structured schedule, as shown in the pictures below.


The name of tasks are clear: Task name = “Zone-Product-Activity”, it is explicit.




Each task has codes (attributes) Zones, Products, Activities levels #1, 2, 3 or more.



If the schedule is well structured, information can be found easily by sorts, filters and groups.


Viewing all articles
Browse latest Browse all 86

Latest Images

Trending Articles



Latest Images