Quantcast
Channel: CUBIX PROJECT MANAGEMENT - 3D Work Breakdown Structure method
Viewing all 86 articles
Browse latest View live

Part #114: Advanced EVM S curves

$
0
0
3D WBS method goes further of project structuration, I call it then 3D Project Management. It is 3D structured projects with advanced project management methods.

For the EVM S curves, I recommend to use paid costs (and not commitments or amounts of invoices received), with payment terms and conditions assigned on schedule’s tasks, in order to obtain the cash out curve. Because, with the cash incurve, it is easy to obtain a cash flow curve linked to the schedule. Therefore, the planned value curve is function of the payments, plus the hours spreaded on the schedule’s tasks. No need to assign resources on tasks, a weight in hours is enough.

Regarding the Earned Value calculation, I recommend to put in place intermediate milestones method on schedule’s tasks. Each milestone has a weight so that if the schedule has no delay then the theoretical earned value S curve is equal to the planned value curve. So, if the schedule is over-time, then there is a variation between the Earned Value and Planned Value curves.

To be noted that Actual Cost curve extension gives the cost estimate at completion. And the earned value curve extension gives the final date estimate. At the intersection, there is the final point of the project.


To be noted also that the planned value late curve is on the graph and is calculated with the schedule.



Part #115: Resource Breakdown Structure (RBS)

Part #116: 3D V lifecycle of an EPC project

$
0
0
Below the 3D V lifecycle of an EPC project (Engineering, Procurement, Construction).

We start and finish with abstract items (Zones, Products, Activities), and at the middle of the cycle we have physical items on the three axis, as for others type of projects.



Part #117: 3D V lifecycle of a NPD project

$
0
0
Below the 3D V lifecycle of an NPD project (New Product Development).

We start and finish with abstract items (Zones, Products, Activities), and at the middle of the cycle we have physical items on the three axis, as for others type of projects.



Part #118: The 5W2H method and the Project Management

$
0
0
3D WBS method answers all the fundamental questions what, how, where, who, when, why and how much. More of that, it put in relationship all these questions.

WHATare we doing ?
We do Product (PBS, Product Breakdown Structure), like IT modules, civil works components, functional systems, equipment, deliverables, etc.

HOWare we doing Products?
We deploy Activities (ABS, Activity Breakdown Structure) on Products to produce them, like design, procurement, installation, etc.

WHEREare the Products assigned?
Products are assigned into a Zone (ZBS, Zone Breakdown Structure), like release, wave of prototype, process unit, geographical area.

WHOis doing the work?
Resources (RBS, Resource Breakdown Structure) which belong to an organization (OBS, Organization Breakdown Structure) do the work.

WHENis the work done?
Tasks (crossing between ZBS, PBS and ABS) are scheduled in the time.

WHYis the work done?
We do the project to obtain the Project/Product Value (ROI/NPV) required.

HOW MUCH is the cost of the project?
Resources (RBS) are assigned to tasks to calculate the cost of the project.

FOR WHAT is the work done?
We work to do Products (PBS) with the physico-functional characteristics required, and the quality level required.



Part #119: N dimensions of a WBS

$
0
0
3D WBS does not say that there are only 3 dimensions (ZBS, PBS, ABS) for the WBS (dimension = elementary tree structure that answer an elementary question), but it says that there are 3 MAIN dimensions in the WBS, it’s quite different! Of course there are N dimensions but only 3 dimensions must be used together (Zone, Product, Activity) for one view of the WBS.

This, because to Work (WBS) is doing (ABS) something (PBS) somewhere (ZBS). There is also the fourth dimension, the OBS which is the Organization.

If you describe your project with 15 tables, like with OMNICLASS tables, then you have to choose 3 dimensions among the 15 tables available to obtain a view of your WBS. For instance, tables 11 (ZBS), 21 (PBS) and 31 (ABS) can be used together, or tables 14 (ZBS), 23 (PBS) and 32 (ABS).

You have to join triplet of tree structures to build a WBS, but of course there are N dimensions in a project, but there are only 4 dimensions linked together for one view of the project (OBS, ZBS, PBS, and ABS).

Some tables of OMNICLASS for instance belong to the same family, I mean it is either Zone, Product, Activity or Organization dimensions. Hence, we can have parallel dimensions to the four main dimensions.


Part #120: Star tetrahedron projects !

$
0
0
As Garrett Lisi’s theory of everything, 8 dimensions can be envisaged for a project.

In blue, the SCOPE dimensions of the 3D WBS : PBS (what?), ABS (How?), ZBS (Where?), and configuration management (For what?).

In red, the VALUE dimensions of the 3D WBS: OBS/RBS (Who?), Cost (How much?), Time (When?), and Value of the Project/Product (Why?).

For reasons of clarity, the dimensions are reduced to a point.


Thanks to Doctor Paul D. Giammalvo for his initial idea: 

Thanks to Stephen A. Decaux for his help, last book 
"Managing projects as investments":

Part #121: Project break down as fractals !

$
0
0
In fractal method, the basic structure repeats, not only at the macro level (the universe for instance) but also at micro and micro micro levels as well. 

For a project it is the same, the star tetrahedron of the project repeats up to the micro level, as tasks. But it is also the same for a project portfolio...

Finally, a project environment looks like that !


I mean that when you structure a program, a project, a task or a projet portfolio, you always ask the same questions: what, how, where, who, why, for what, how much and when. Whatever the level, it is the same, as fractals.


Thanks to Doctor Paul D. Giammalvo for his initial idea: 


Part #122: Thoughts of Xavier LEYNAUD

$
0
0














When I work on the concept that Jean-Yves develops long time ago, it was specially because I was “fed up” with the hierarchical approach that imply most of the WBS, and the fight about its standardization.

I study conception for management software engineering in my youth, and I always keep a fascination to the relation database model.

So my eager was to find a way to modelize something and respond to everybody in the company by turning it up in every senses in one instant.

So as I work mainly in my youth with Artemis, with the very structured codification environnement of oil and gaz (Mobil and then Exxon), I simply use without knowing it this 3D approach to do the trick.

Then I met Jean-Yves, that push the concept so far that new frontiers appears (in addition to the speed to develop a schedule).

In particular, what is very important for me is the following:
  1. 2 of The 3 type of codification (ABS & PBS) are fully able to be standardize in the company without fight (even if you should be careful with” PBS” that in fact is 2 codes and decompose it for the exercise in pure PBS and SBS to match the need of some of the phase of the ABS because you began to think functionnaly, then you go through the product, before finishing functionnaly)
  2. ZBS is specific to each project and can support the instantiation of the product (but could follow some guideline in its definition in particular the unicity of each code -  no overlap-)
  3. Different level of each of the structure could be mixed at different stage of the project and depending the use of your WBS to create the project WBS (you can have a detail difference in your WBS for procurement and manufacturing because you manufacture some items for example), and the approach is still coherent,
  4. When you create your mix with the OBS to obtain the share of work, you obtain as more difficult interface than the fundamental dimension of the WBS component are far in the concerned branch of the code (that lead to create an allocation of the package reducing those gaps to simplify the interface).
Thus I without knowing it implementing it till many years, but with the full modelization of Jean-Yves is able to succeed in standard codification in my company because I say no more froze hierarchical WBS, just ABS, PBS, SBS and rules to create your ZBS. Then NO PACKAGE WITH TOO GREAT GAP ON EACH OF THE DIMENSIONS (or with logical huge gap like company who you subcontract high level specification and functional test & commissioning).

WBS is dead, because 3D WBS allow you to keep it “relational” instead of hierarchical and this does the trick with a lot of things, specialy with those “fuc…” computerized financial management systems called ERP that most of the time impose to you a 20 digits codification (when not more) to link everything when a anonymous code will be greater if you use the 4 codes composing the 3D.



Xavier LEYNAUD
Head of planning and load management
ALSTOM RENEWABLE POWER







Part #123: Thoughts of Doctor Paul D. GIAMMALVO

$
0
0



The trend is clearly towards MULTI-DIMENSIONAL WBS structures. (Relational Database vs Flat File)

I believe one of the world's leading authorities on multiple WBS structures is Jean Yves Moine. Take the time to link up with him if you get the chance.

CSI did this with Master: 

and Uniformat
the Norwegians did it for offshore oil and gas with Norzok Z-014:
and now we are urging our IT and Telecommunications clients to recognize the value and importance of not only STANDARDIZING the WBS but also creating multi-dimensional WBS (3D WBS).



Dr. Paul D. Giammalvo
CDT, CCP, MScPM, MRICS, GPM-M
Develop and Deliver Graduate Level, Blended Learning Programs in Applied Portfolio, Program and Project Management

Part #124: 3D WBS process of projects structuration

Part #125: Project cube synoptic

$
0
0
It looks like that...
We find the WBS: ZBS, PBS and ABS. And also "For what" which belongs to the scope items too.
And we find Project Value dimensions: why, who, how much and when. 



Part #126: Conference 3D WBS at the SMP

$
0
0
In september 2014, I will do a conference at the Swiss Project Management Association (SMP). 

Sorry, it will be in French...




Part #127:The Value Breakdown Structure (VBS): Features & Benefits

$
0
0
The value solves the question WHY 
of the 3D WBS modeling...


















Copyright 2014: Stephen A. Devaux, Analytic Project Management

Every project and program is an investment, undertaken to generate benefits that are of greater value to the sponsor/customer/investor than the cost of the resources invested. In this sense, the relative success or failure of the project can be represented as expected project profit, i.e., the difference between the total cost of the resources invested and the value that, at completion, the project is expected to generate.

The above stipulation illustrates a serious misunderstanding in project metrics: the conflation of the unfortunately misnamed “earned value” with the project’s “business” or “investment” value. Earned value is always based on resource usage: the total resource budget or the budget for labor or for a specific material. But this has nothing to do with the value the project is expected to generate. Indeed, no intelligent sponsor would ever invest S1M in a project the product of which he values at exactly $1M – even the least project risk and shortest project duration would dictate that the sponsor would only invest $1M if he expects it create more than $1M in value. And sometimes that expected value may be much greater than $1M – an enabler project, for instance, such as a new platform on which many valuable systems may be loaded, may create value and opportunity worth many multiples of the platform-creation’s project budget. Yet that budget would be the basis for the project’s earned value.

Value, in the form of ROI or NPV or any other name, is the raison d’etre of every program and project, and is carefully analyzed and tracked on all other types of investments. Yet, on projects alone (where the project team often has the ability to make decisions that can greatly impact value), this driving investment metric is often never estimated, and even when it is, is not tracked and/or conveyed to the project team as a precision metric for decision-making.    

The project’s value is created by the scope: mostly the product scope, but occasionally with some value added by the project scope (e.g., improved organizational skills with a new manufacturing technology). Yet while the resource budget is loaded into the elements of the work breakdown structure and summed to the top to create both the budget and the earned value baseline for each summary element and for the whole project, the project’s expected value, even if estimated, is not decomposed to the work elements.

Value behaves differently from cost, yet tracking it is no less important. Whereas cost is always additive (the sum of the dollar costs of five detail activities ALWAYS is equal to the dollar cost of their parent summary activity), value is not. The value of two activities may be less OR more than the sum of each, i.e., they may either duplicate some of the other’s value or kindle each other’s value.

  1. Mandatory activities/work packages/projects have a value equal to that of the entire project/program: if we build an airplane valued at $1M but leave out the left wing, the value of the project is zero unless and untilthat wing is added, making its value-added $1M. Interestingly, its right wing is exactly the same! But the value of the two (mandatory) wings does not sum to $2M – it only sums to the $1M value of the whole project.
  2. Optional activities have a value equal to the difference between the total expected project value and what the project would be worth if we did all the other work except that optional work (activity/work package/project within a project/program).
The value breakdown structure (VBS) may be identical in format to the WBS, but will simply be loaded with different data (dollars of value instead of cost) and not necessarily be additive up the branches. It provides the following benefits:
  •     Prioritization of work based on classification of mandatory vs. optional work;
  •     Prioritization of work based on classification of different optional work based on its relative value;
  •     Recognition of project value accumulation on terms other than earned value (i.e., cost);
  •     Recognition of accrued (i.e., salvageable) project value if considering project truncation;
  •     Quantification of the value impact of scope reduction;
  •     Identification of work whose value-added is less than its true cost. This is particularly important whenever there is a change in the schedule such that new optional work migrates to the critical path and acquires critical path drag and drag cost (true cost = resource cost plus drag cost).  
             
Stephen A. DEVAUX
President, ANALYTIC PROJECT MANAGEMENT
Author, Instructor, & Consultant
Author of "Managing projects as investments"
http://www.crcpress.com/product/isbn/9781482212709


Part #128: Project control consulting and training

$
0
0






Do you need:

  • to create standards WBS in your company?
  • to do a schedule quicky and well?
  • to do the cash-flow curve linked to the schedule?
  • to manage both time and cost together?
  • To identify the interfaces of your project?
  • a training on planning or 3D WBS?
  • a training on PRIMAVERA P6 or MS PROJECT?
  • a personnalized VBA tool for costing, cost control or risk analysis?
  • Another service in project control?


Contact Cubix Project Management company, your partner in project control.

web site: http://www.cubixpm.fr
email : jean-yves.moine@cubixpm.com



Part #128: Another view of the WBS

$
0
0
The task is the last element of the WBS, it is at the crossing between ZBS, PBS and ABS; knowing that we can take the level of our choice on all the three tree structures to produce a Task.



Part #128: Consulting in Project Control

$
0
0

Do you need: 

  • To create standards WBS for your company? 
  • To Plan your project well and quickly? 
  • To create a cash-flow curve related to schedule? 
  • To Manage both costs and time together
  • To Identify interfaces of your project (risks)? 
  • A VBA EXCEL tools, for costing or cost control? 
  • Monte Carlo risk analysis with EXCEL or MS PROJECT? 
  • A Training on planning or 3D WBS
  • A Training on Cubix360, MS PROJECT or PRIMAVERA P6
  • Another service project control? 

Contact the company Cubix Project Management, your partner in project control

website: http://cubixpm.fr 

email: jean-yves.moine@cubixpm.com


Part #129: Another view of the 3D WBS

$
0
0
For one Product line, the crossing between ABS and PBS is standard. For two projects of the same Product line, the changes are the Zones.

In the picture below, ABS and PBS tree structures are projected on the axis of the square. We can see that the triplet {ZBS, PBS, ABS} forms one Task. We can choose the level that we need on each tree structure to form one Task, for instance ABS level #2, PBS level #2 and ZBS level #1.

As shown in the WBS matrix, we can assign several ZBS elements to the couple {PBS, ABS}. In other words, some process (ABS) associated to one Product (PBS) can be repeated in different Zones (ZBS).



Part #130: Cubix360, the software that applies 3D WBS method

$
0
0
I created with myAMS Cubix360 software that is the only software that apply 3D WBS method. It allows to build quickly and well, and with method, MS PROJECT or PRIMAVERA P6 schedules.

To buy Cubix360, write me an email here: jean-yves.moine@cubixpm.com



Part #131: 3D V lifecycle of a building construction project

$
0
0
Below the 3D V lifecycle of a building construction project.

As you can see, there are always 3 dimensions for the Work (ABS, PBS, ZBS) and we can add the fourth dimension OBS to describe the whole schedule.

To be noted that OMNICLASS, that is a standard for Building construction, has 15 tables but not 15 dimensions ! Because each table belongs to either PBS, ABS, ZBS or OBS. Each table answers only one elementary question: What?, How? Where? or Who?. So, it must be clear that OMNICLASS has only 4 dimensions.
Viewing all 86 articles
Browse latest View live